Ampol transition program commenced in Feb 21 with a target of approx. 1200 Ampol sites to be transitioned by mid-2022. At mid-October, approx. 650 Ampol sites have been successfully transitioned. Transition works have been undertaken is all states except NT during 2021. Site transitions are completed in a 2 week time frame. Painting & refresh works completed during ‘week1’ & Ampol brand transition works are completed during ‘week 2’. Each week the Modus PIP team are managing up to 30 site transitions including all site project administration, contractor logistics, contractor safety performance, COVID compliance as applicable and site brand standards compliance. Approx. 465 contractors have been inducted int to the Ampol transition program nationally
Project Size
1850+ Ampol sites
Delivery
2 weeks per site
Service
Trade Management